29 Meredyth Road
We delivered a SuDS Strategy for 29 Meredyth Road to discharge a pre-commencement planning condition. The report included runoff calculations, SuDS specification, drainage layout, and maintenance details. The condition was discharged without comment, allowing construction to proceed smoothly.

We supported the discharge of a pre-commencement planning condition requiring a Sustainable Drainage Systems (SuDS) Strategy for a proposed ground floor extension at 29 Meredyth Road.
Our team provided a detailed report addressing all elements of the condition, including:
Full calculation of existing and proposed runoff rates and attenuation volumes, achieving over 50% reduction in line with Local Plan Policy CE2(g), factoring in climate change and all contributing flows.
Specification of SuDS features including permeable paving and sub-base attenuation.
Drainage layout plans clearly illustrating surface water conveyance, SuDS location, capacity, and connection to the sewer system.
Maintenance guidance, access provision, and structural profiles for all SuDS components.
The planning condition was formally discharged with no additional comments from the Council, enabling development to proceed without delay.