BRE 365 Soakage Test Before Planning: Why Infiltration Left Subject to Testing Gets Refused
A BRE 365 soakage test measures how fast water drains into the ground at the place and depth of a proposed soakaway. Councils and Lead Local Flood Authorities (LLFAs) now often want the result before they accept a drainage strategy that relies on infiltration. A strategy that leaves infiltration "subject to testing" can be refused at planning or condition stage, because nobody can check that the hierarchy was followed. Below: when the test is needed, what was refused without it, and what to submit when you cannot test yet.
Drainage condition refused, or not sure whether to test first? Send us the decision notice and your strategy through our fee proposal form. Our SuDS strategy service covers the strategy, the calculations and the drawings.
What a BRE 365 soakage test is
BRE Digest 365, Soakaway design, sets the test. A trial pit is excavated at the position and depth of the proposed soakaway, filled with water three times and timed as it drains. The infiltration rate, in m/s, comes from the time the level takes to fall from 75% to 25% of the effective depth. North Yorkshire's infiltration guidance states that "the lowest value infiltration rate per trial pit should be used, it should not be averaged". CIRIA C753, The SuDS Manual, sets the factors of safety applied to the result.
Season matters. Groundwater is usually highest in winter, so a rate measured in a dry summer can overstate what the ground takes in February.

Illustrative AI image; not a real site or an AFC project.
Why "subject to testing" gets refused
The Planning Practice Guidance on flood risk and coastal change (paragraph 056, Reference ID 7-056-20220825) sets the order in which surface water destinations are considered: "into the ground (infiltration); to a surface water body; to a surface water sewer, highway drain, or another drainage system; to a combined sewer." The Defra National Standards for Sustainable Drainage Systems (2025) keep that order below collection for non-potable use. A sewer or a watercourse is accepted only once infiltration has been tested or ruled out with evidence (Figure 1).

Figure 1: The drainage hierarchy, with what the council needs to see before each step down. Drawn by AFC from PPG paragraph 056 and clause 1.2 of the National Standards.
Two neighbouring single-dwelling plots at Newport Pagnell, Milton Keynes, show what happens when that evidence is missing. Both had planning permission with a pre-commencement surface water drainage condition. The drainage strategy approved with each permission had left infiltration open. On 19 August 2026 Milton Keynes City Council refused the drainage details for both plots. The refusal reason for the drainage condition on Plot 1 opens with infiltration:
"The previously approved Drainage Strategy (Ref. 1288) identified infiltration as a potentially feasible method of surface water disposal subject to satisfactory infiltration testing. Instead, the submitted detailed drainage scheme now proposes discharge to the existing private surface water drainage system and no infiltration testing results have been provided. As such, insufficient evidence has been provided to demonstrate that the drainage hierarchy has been appropriately followed."
Infiltration was the first of several grounds in the same reason. The others were groundwater, the private sewer's outfall (not proved), and errors in the hydraulic calculations. A separate contamination condition was also refused.
The Plot 1 scheme was small: about 0.021 ha of roof and paving, including 10% for urban creep, stored in lined permeable paving and released at 2.0 l/s to a private sewer. It stepped past infiltration with neither test results nor evidence ruling it out. The officer report notes that the council's Level 1 Strategic Flood Risk Assessment (Appendix G) shows groundwater at or near the surface there. The ground investigation recorded groundwater at about 1.4 m below ground in May 2026, in prolonged dry weather. The drainage scheme did not use that evidence. Nor was the fallback outlet proven, since the private sewer had not been shown to have an outfall.
An amended drainage statement sent in August, after the objection, was not assessed: "amendments to Discharge of Condition applications cannot be accepted and thus only the original submission documents will be assessed" (officer report, page 2). Where a council works that way, the first submission has to be complete.
When councils want the test before the application is decided
Clause 1.14 of the National Standards makes infiltration "dependent on the ground conditions being suitable and adequate infiltration rates being identified using the assessment methods detailed in standard 3". Local guidance sets when the results are expected.
Arun District Council. Its infiltration testing guidance note (updated 24 October 2025) requires tests strictly to BRE Digest 365. It says testing "is particularly critical if a site relies on the use of infiltration into the ground as the only option to drain surface water", then continues: "Examples of alternative options could include nearby watercourses or surface water sewers. In those instances, the viability of infiltration is expected to be demonstrated prior to planning permission being granted." Trial pits are to be tested in winter or spring, and "Winter (December to February) is preferred and encouraged."
Essex County Council as LLFA. The Essex Design Guide requires full detailed infiltration testing to BRE 365 and CIRIA C753 "For full applications or where necessary for discharge of conditions applications". At outline stage it accepts preliminary ground investigation or a desk study, with testing later.
North Yorkshire Council as LLFA. Its supplementary infiltration guidance states that "adequate infiltration tests should be provided for all development sites, including outline and full applications".
Where your council asks for results at application stage, an assumed rate is likely to draw an objection.
When a condition is accepted instead, and the catch
A council may leave the drainage details to a condition when it is satisfied that the site can be drained somehow. On a dental surgery extension in Lydney, Forest of Dean, the flood officer found AFC's planning-stage strategy unacceptable in July 2026 because "no site-specific infiltration testing has been provided", among other points. A month later the officer accepted a pre-commencement condition, "on the basis that a public combined sewer exists in the proximity it can be safely assumed a drainage destination is available." The proven outlet allowed the condition. The full sequence is in our guide to discharging a surface water drainage condition.
The Milton Keynes refusals were at condition stage, on permissions granted two and three years earlier. The same decision notice allows a desktop study and "a worst-case infiltration rate" where the site cannot be accessed before planning approval, then adds that "soakage testing will be required at a later stage to clarify this." A condition defers the test; it does not remove it.

Figure 2: Test now or later. A screening aid drawn by AFC from the decided cases in this article; the council's own guidance decides.
What to write when you cannot run a BRE 365 soakage test yet
Where the site is occupied, built over or inaccessible, the strategy has to show the hierarchy was followed on the evidence that exists.
Published ground data. BGS geology mapping and the nearest borehole records on the BGS GeoIndex, with any groundwater strikes and their dates. Our infiltration potential map is a first screen; it is not a substitute for a test.
Groundwater. The council's Strategic Flood Risk Assessment groundwater mapping and any site investigation readings, with the season they were taken in.
Constraints. Contamination, mining or ground stability records, and source protection zones.
An assumed rate stated as an assumption, with its source, and the condition under which it will be confirmed by test.
A lined fallback, sized and drawn, with an outlet proved from the sewer records or a watercourse survey, so the site drains even if the test fails.
Or rule infiltration out on that evidence from the start, and design lined storage. A householder extension in Teddington was refused in 2025 on surface water drainage, with a design by others, and the appeal was dismissed. AFC's strategy for the fresh application ruled infiltration out on the clay and the high groundwater risk. It used 370 litres of rainwater planters with a flow control to the public surface water sewer. Permission was granted in June 2026 (case study).

Illustrative AI image; not a real site or an AFC project.
The traps
Testing in summer. A dry-season rate overstates what the ground takes when groundwater is high. Record the test date and the groundwater level found.
The wrong depth or place, or one pit for a large site. Test at the base and position of each infiltration feature.
Rates that do not match. Different rates in the strategy, the calculations and later letters, or a slipped exponent (1 × 10⁻⁵ against 1 × 10⁻⁶ m/s is a factor of ten), give the LLFA a reason to reject all of them.
Shallow groundwater. Clause 4.16.1 of the National Standards requires, for SuDS wholly relying on infiltration, "a minimum depth of unsaturated ground of 1m between the base of any infiltration feature and the maximum likely groundwater level". A soakaway 1.5 m deep with groundwater at 2 m fails, whatever the rate.
Soakaways too close to buildings. Hastings Borough Council's soakaway advice note states that "The soakaway must be at least 5m away from any building." A small plot may have no position that meets it.
Frequently asked questions
Do I need a soakage test before submitting a planning application?
If the drainage relies on infiltration, many councils and LLFAs expect BRE 365 results with the application. Others accept a desktop assessment if a fallback outlet is proven. If infiltration is not in the design, record the evidence that rules it out.
Can infiltration testing be left to a planning condition?
Sometimes, where the council is satisfied the site can drain another way, for example to a nearby public sewer. The tests then come back when the condition is discharged. Two Milton Keynes drainage conditions were refused in August 2026, among other reasons because the detailed scheme had neither test results nor evidence ruling infiltration out.
What is a BRE 365 test?
A trial pit at the depth and position of the proposed soakaway, filled with water three times and timed as it drains. The lowest of the three rates is used.
What infiltration rate is too low for a soakaway?
There is no single national cut-off. The soakaway has to empty within the time the council's or LLFA's guidance sets, with the CIRIA C753 factor of safety applied. For deep bore soakaways, for example, North Yorkshire's infiltration guidance lists among its design parameters that "the storage volume of the soakaway should be half empty within 24 hours". If the measured rate cannot meet the council's requirement, the design steps down the hierarchy.
What if the ground is clay or the groundwater is high?
Infiltration is then usually ruled out on the stated evidence, and lined storage discharges at a controlled rate to a watercourse or sewer.
My drainage condition was refused for no infiltration testing. What now?
Commission BRE 365 tests at the right depth and season, or assemble the evidence that rules infiltration out, then make a fresh, complete condition application. Our guide to discharging a surface water drainage condition lists what it should contain.
Can I use an assumed infiltration rate from geology maps?
As a stated planning-stage assumption with a lined fallback to a proven outlet, sometimes. As the rate for a design to be built, no: that comes from tests on the site.
Ask us before you submit
AFC prepares SuDS strategies and drainage condition submissions, and says at the outset whether infiltration testing is needed first. Send your decision notice or layout through the fee proposal form. National policy on SuDS is covered in our post on SuDS under the NPPF 2026.