top of page
Flowchart of how Enfield handles an application: 21 days to supply missing items, then decided as submitted with no further information or amendments

Flood Risk Assessment in Enfield: Why the FRA and SuDS Pro-forma Must Be Complete at Validation

Nick
Nov 17
8 min read

A flood risk assessment in Enfield has to be complete when the application is validated. Enfield's standard acknowledgement letter says a validated application "will be considered as it is", with no further information, extension of time or amendment. A Lead Local Flood Authority (LLFA) comment that the FRA does not answer can therefore end in a refusal and a new application. This guide sets out when Enfield asks for an FRA and the SuDS pro-forma, what each must contain, and what eight 2026 condition refusals show about Enfield's SuDS officers.


Enfield asked for an FRA and SuDS pro-forma at validation? Send us the council's letter and your drawings for a fee proposal, and we will make the submission complete first time.


Enfield decides applications as submitted

Enfield Planning Support's acknowledgement letter (October 2026) sets two rules. The first covers missing documents:


"You will need to provide outstanding information within 21 days. After this time your application will be returned, and your fee refunded, less our administration fee."

The second covers what happens after validation:


"Once an application is validated, it will be considered as it is. This means that you won't be able to provide additional information waived by an Article 12 Notice, request an extension of time, or make amendments to your application unless you have first sought formal pre-application advice for the same scheme."

Condition applications are treated the same way. The officer report for 26/01935/CND carries this informative: "The London Borough of Enfield does not accept revisions or amendments to planning applications once they have been validated. Applications are determined strictly on the basis of the information submitted at validation."


In practice, an LLFA question the FRA has not answered leads to a refusal, or to a condition that a complete report would have avoided.

Flowchart: application submitted, acknowledgement letter, 21 days to supply missing items, validated, decided as submitted with no additional information, extension of time or amendments; formal pre-application advice is the only exception named

Figure 1. How Enfield handles an application once it is validated (from the standard acknowledgement letter, 28 October 2026).


When Enfield asks for a flood risk assessment

Policy DMD 60 of the Enfield Development Management Document (2014) sets wider triggers than national policy:


  • "Development proposals of 1 hectare or greater in Flood Zone 1";

  • "All proposals for new development located in Flood Zones 2 and 3";

  • "All proposals in groundwater flood risk areas that involve the creation of useable space below ground";

  • "All proposals for new development identified as being at risk from surface water flooding in the SWMP".


Enfield's local validation lists (non-householder, 25 March 2024; householder, 6 November 2023) add two more triggers. The first is a ground-level extension or basement in a surface water flood risk area. The second is a new building or extension "within 8m of a watercourse (including culverted)".


So a single-storey rear extension in Flood Zone 1 can need an FRA. Our guide to flood risk assessments outside a flood zone explains which map counts.


In autumn 2026 a ground-floor rear extension to a flat in Flood Zone 1, inside the surface water flood extent, was held at validation. The council told the applicant the site was in a surface water flooding area, so an FRA was required. It pointed to its SuDS page. A short surface water note from the architect was already in hand, and the council still asked for an FRA.


What a flood risk assessment in Enfield must contain

A map-based note shows that the site lies in a surface water flood extent. It does not give depths, levels or flow routes. The note in that case said so itself: the mapping "does not provide property-specific flood depths, velocities or threshold levels". The FRA adds:


  • ground levels and the 1 in 100-year (1% AEP) plus climate change surface water level at the footprint;

  • the finished floor level set against it;

  • overland flow routes, kept open;

  • level-for-level compensation for any flood storage the footprint removes;

  • safe access and a flood management or evacuation plan;

  • residual risk and resilience measures.


The validation lists ask for an evacuation route in the "Very Low Hazard Level" according to FD2320. Our guide to flood emergency plans covers what goes in one.

Illustrative AI image; not a real site or an AFC project. A rear extension to a ground-floor flat with its patio one step above a shallow sheet of rainwater on the lawn after a downpour

Illustrative AI image; not a real site or an AFC project.


Floor levels: the 150 mm and 300 mm figures

DMD 62 paragraph 8.5.18 states: "Finished floor levels for these developments should be set at least 300mm above the 100 year plus climate change flood level." It adds: "For surface water flooding, a 100mm freeboard instead of 300mm may be considered."


The 2024 validation lists go further for surface water. They advise that finished floor levels "must be at least 150mm above the 1 in 100 year (plus climate change) surface water flood depth and 300mm above the 1 in 100 year (plus climate change) fluvial flood depth".


The LLFA applies 150 mm. In a 2026 objection to a householder extension in Flood Zone 1, it gave the surface water level as about 24.55 mAOD. The proposed floor at 24.52 mAOD was 30 mm below it. The LLFA asked for 150 mm above the flood level (at least 24.70 mAOD), level-for-level compensation and an FD2320 "Very Low" hazard evacuation route.


The flood level is the Risk of Flooding from Surface Water (RoFSW) depth for the 1 in 100-year plus climate change event added to the ground level at the footprint. Where raising the floor is not possible, see finished floor levels in flood zones.

Section through a rear extension showing the 1 in 100-year plus climate change surface water level at about 24.55 mAOD, a refused floor level of 24.52 mAOD and the required floor level of at least 24.70 mAOD, 150 mm above

Figure 2. Setting the floor level in an Enfield surface water area (levels from a 2026 LLFA objection).


The SuDS pro-forma and what goes in it

Core Policy 28 of the Core Strategy (2010) requires SuDS "in all developments, irrespective of the flood risk at individual development sites". DMD 61 requires minor schemes to "seek to achieve greenfield run off" and to include "at least one 'at source' SuDS measure".


The validation lists state: "All relevant proposals require a completed SuDS pro-forma." Enfield's standard condition points small schemes to "the SuDS Proforma for minor developers" on its SuDS page. The submission should include:


  • a calculated greenfield runoff rate, and the discharge rate against it;

  • storage counted from void space only;

  • every roof and paved area tied to the feature that serves it;

  • infiltration test results, or the reason infiltration is not used;

  • exceedance flow routes;

  • a maintenance plan.


Plan of a rear extension and patio with the extension roof draining to a water butt and rain planter, the patio as permeable paving and a re-routed roof slope to a rain garden, with a catchment table

Figure 3. Tie every roof and paved area to the SuDS feature that serves it.

Illustrative AI image; not a real site or an AFC project. A rear extension whose downpipe feeds a water butt overflowing to a rain garden, with a permeable block-paved patio

Illustrative AI image; not a real site or an AFC project.


What Enfield's SuDS officers refused, and why

All of these were the applicants' own submissions; none was AFC's work.


Reference

What was missing

What would have passed

26/02226/CND

No source control; "as existing" drainage on a change of use

A retrofit measure, such as a water butt and planter

26/02046/CND

Lined geomembrane paving and planters; areas not tied to features

Unlined build-ups and a catchment table

26/02129/CND

No calculated greenfield rate; hierarchy skipped

QBAR and return-period rates; each step assessed

26/02150/CND

Pod storage taken from gross dimensions

Void volume only

26/02276/CND

Drawings and infiltration tests deferred

Levelled layout, BRE 365 results, calculations

26/02614/CND

Strategy "suitable", but no levelled drainage plan

Every feature with sizes and levels

26/03187/CND

Soakaway with no infiltration test

Water butt or rain planter


Partial storage can pass with a clear case. Condition 26/02144/CND was discharged on 23 June 2026 with 6.27 m³ against an 11.72 m³ target. The garden was 23 m² on London Clay, and the shortfall was justified as best endeavours. That was also the applicant's own submission.

Eight Enfield SuDS condition refusals in 2026 with what was missing and the fix for each

Figure 4. Enfield SuDS condition refusals in 2026 and what would have passed.


The householder SuDS condition: three refusals

Enfield's standard householder condition, quoted in the officer report for 26/03187/CND, reads: "Prior to above ground works, details of source control SuDS shall be submitted to and approved in writing by the Local Planning Authority. Source control SuDS measures include green roofs, rain gardens and permeable paving."


26/03187/CND, disapproved 25 August 2026. The strategy covered 11.27 m² of new impermeable area. It used 25 m² of permeable paving and a small soakaway, 2.6 m³ against the pro-forma target of 2.60 m³. The pro-forma returned "Adequate storage provided". No infiltration test had been done. The SuDS officers commented: "We do not recommend the discharge of the condition as on site infiltration has not been completed to allow the acceptance of a soakaway. Source control SuDS measures such as a water butt or rain planter should be utilised."


26/02044/CND, disapproved 2 July 2026. A lower ground floor extension with no groundwater assessment. The senior SuDS officer wrote: "Groundwater Flood Risk Assessment has not been provided as feasibility of the development." A further point read: "All proposed impermeable area must drain via source control". It was the second refusal for the same condition, after 25/03573/CND in December 2025.


26/02046/CND. Lined paving, as in the table above.


Without a BRE 365 result, the design should rest on source control that does not rely on infiltration: rain planters, water butts, green roofs. A soakaway can be offered "subject to a BRE 365 test", with the non-infiltrating measure as the design. A basement or lower ground floor needs a groundwater assessment. The general process is in how to discharge a surface water drainage condition.

Three options for 11.27 m2 of new impermeable area: an untested soakaway refused under 26/03187/CND, a rain planter fed from the roof, and a water butt overflowing to a planter

Figure 5. What Enfield's SuDS officers named instead of an untested soakaway.


A first-time-complete checklist

  • Floor level against the 1 in 100-year plus climate change surface water level, with 150 mm freeboard.

  • Overland flow routes kept open.

  • Level-for-level compensation where the footprint is in the flood extent.

  • An evacuation route at FD2320 "Very Low" hazard.

  • At least one at-source SuDS measure, with plan, specification and maintenance.

  • The greenfield rate and the discharge rate.

  • Infiltration test results, or the reason infiltration is not used.

  • A levelled drainage layout drawing.

  • The completed pro-forma.


A similar package for a north London site is in our Edgware FRA and SuDS case study.


Validation deadlines

The acknowledgement letter gives 21 days to supply missing items once the council has explained what is missing. An FRA needs levels, mapping and a floor-level check, so commission it before submitting. If the application is returned, the fee is refunded less an administration fee.

Why does Enfield need a flood risk assessment if I'm in Flood Zone 1?

DMD 60 and the validation lists require one for development at surface water flood risk, and for ground-level extensions in a surface water risk area, whatever the flood zone.

What is the Enfield SuDS pro-forma and which one do I use?

A form recording areas, storage and SuDS features. Enfield's condition points small schemes to the minor-development pro-forma on its SuDS page.

Can I send more information after my Enfield planning application is validated?

Not unless formal pre-application advice was sought for the same scheme. The acknowledgement letter says a validated application "will be considered as it is".

How high does my floor level need to be in an Enfield surface water flood area?

At least 150 mm above the 1 in 100-year plus climate change surface water level, as advised in the validation lists and applied by the LLFA.

Is a short surface water statement enough instead of a full FRA?

In the autumn 2026 case above it was not. A map extract gives no depths or levels, so it cannot set a floor level.

Can I use a soakaway for an Enfield SuDS condition without a soakage test?

26/03187/CND was refused for that reason. Design with a water butt or rain planter, and offer infiltration only subject to a BRE 365 test.


For a flood risk assessment and SuDS pro-forma in Enfield, request a fee proposal through the website form with your drawings and the council's letter.

 
 
 

Comments