Environment Agency Product 4 Flood Data: What It Is, How Long It Takes, and What to Do When You Get Products 5, 6 and 7 Instead
Environment Agency Product 4 is the site data package an FRA needs for a site in Flood Zone 2 or 3: the modelled flood levels in mAOD around your site, with the defences, past floods and climate change allowances for the area. The EA now calls it "flood risk assessment data". It sets your design flood level, and from that the floor or plant level. This guide covers what it contains, how to order it and how long it takes, how to read the level for your site, and what to do when the EA sends Products 5, 6 and 7 instead.
The examples are AFC's own jobs from 2025 and 2026, including a standby generator in West Bridgford that went from an EA objection to planning permission once the Product 4 level was in the FRA.
Waiting on EA data, or holding files you can't read? We order it, read it and put the level in your FRA. Request a fee proposal or see our flood risk assessment service.
What Environment Agency Product 4 is
Product 4 is a PDF package prepared by the local EA team for a site you draw on the Flood Map for Planning. The EA's guidance on flood risk assessments for planning permission (updated 28 May 2026) describes it as "a detailed FRA map". Where available, it shows detailed flood data, flood defence locations and attributes, data on past flood events, modelled flood levels and extents, and flood defence breach hazard information.
The packages now carry a new name. The one AFC received for West Bridgford in October 2025 is headed "Flood risk assessment data" and says on its first page: "This information was previously known as a product 4." Consultants, councils and EA officers still call it Product 4.

Figure 1. The EA's new name for Product 4, on the West Bridgford package (EIR/2025/36206).
The covering letter of the same package sets out the flood zone, the probability bands, the historic flood record and the climate change allowances for the location before any levels appear. For West Bridgford it gave Flood Zone 3, historic fluvial flooding in 1932, 1946 and 1947, and peak river flow allowances of 29% (central), 39% (higher central) and 62% (upper).

Figure 2. The first page of a Product 4 (West Bridgford, October 2025): flood zone, probabilities and climate change allowances before the levels.
The package lists its own contents. The West Bridgford one gives, in this order: surface water and other sources of flooding, the models used, terminology, the flood map for planning, past floods, flood defences and their attributes, information on reduced risk because of defences, modelled data, strategic flood risk assessments, information about the data, flood risk activity permits, and help and advice.
It also says what to do with it: "You can use this information as part of a flood risk assessment for a planning application. To do this, you should include it in the appendix of your flood risk assessment."

Figure 3. What the package contains, and the EA's advice to put it in the FRA appendix.
Products 1 to 8: which ones an FRA needs
The same gov.uk page lists the products available through the Flood Map for Planning. Its advice is direct: "For all development you should request product 1 and product 4." If the FRA will use detailed hydraulic modelling held by the EA, "you are also likely to need products 5, 6 and 7."
Product | What the EA says it is | When an FRA needs it |
|---|---|---|
1 | A copy of the flood map: Flood Zones 1, 2 and 3, defences, main rivers, water storage areas | Every FRA; download it from the map |
2 | Not listed in the current guidance | Not available |
3 | "This product has been discontinued" | Not available |
4 | "A detailed FRA map": flood data, defences, past floods, modelled levels and extents, breach hazard | Every FRA in Flood Zone 2 or 3 |
5 | "A report which includes flood modelling and hydrology reports" | When you rely on or check an EA model |
6 | "The model output data and all the reports in product 5" | When you read levels or depths from grids |
7 | "The Model Input Data, and all the reports in product 5" | When you re-run or extend the model |
8 | "Flood defence breach hazard information", included in Product 4 where available | Defended sites with a breach risk |
The quoted words are the EA's own, from the planning permission guidance. The right-hand column is AFC's reading of when each is needed.
How to request Product 4, and how long it takes
The request goes through the Flood Map for Planning. Find the site by postcode or place, draw the boundary of your site, then for Product 4 "input your name and email address on the page for your development site and submit it."
The red line matters. Draw the whole site, including the access, the garden and any land you will regrade, because the EA returns data for the area you draw. A boundary that misses the footprint can leave you with data for the wrong land.
On timing, the EA states: "The local Environment Agency team will send product 4 information to you for that location within 20 working days." That is the only official figure. The gov.uk pages give no charge for Product 4; charging information was removed from the guidance in 2016.
For Products 5, 6 and 7 the route is different. You "need to find the contact details for the local Environment Agency office", which the Flood Map for Planning gives on the page for your site.
In AFC's recent jobs the data came faster than the 20-day limit. These are examples, not promises:
a householder site in Warwick District: Product 4 ordered on 27 October 2026, received on 5 November 2026, about 9 days;
a householder extension at Dorney, Buckinghamshire: about 9 days in August 2026.
Order it on the day the job is instructed. On both jobs, the date the data arrived set the date the FRA could be finalised.
Reading a Product 4: nodes, sample points and the level at your site
A Product 4 can hold more than one model. The West Bridgford package used two: "Greythorne Dyke, Capita Aecom, 2020" and "River Trent at Nottingham, Black and Veatch, 2010 and Climate Change 2016". For each, it gives flood extent maps and two kinds of level.
1D node levels are points along the river channel, with a level and a flow for each event. They tell you how high the river runs. They do not tell you the level on your site.
2D sample points are a grid of points across the site boundary, each with a height in mAOD and a depth in metres for each event. These are the levels on the land itself.

Figure 4. The 2D sample points across the West Bridgford site, River Trent model, 1% AEP +30% height.

Figure 5. The level table: 23.82 to 23.83 mAOD across the site for 1% AEP +30%, defended.
At West Bridgford the Greythorne Dyke model returned "NoData" at every sample point: no flooding on the site from that watercourse. The River Trent model gave 23.82 to 23.83 mAOD at the wet points for the defended 1% AEP +30% event. The depths at those points range from 0.03 m to 0.28 m, because ground levels vary across the site. The FRA took the level at sample point 19, closest to the generator, and quotes a flood depth of 0.22 m at the site. The table gives 0.19 m at point 19 itself and up to 0.28 m elsewhere on the site, so a depth always needs the point it applies to.
The 1D River Trent nodes nearest the site, nodes 5 and 6, give 24.42 and 24.14 mAOD for the defended 1% AEP event. Those are channel levels on a defended river. The site level is the 2D figure.
Which event and which climate change allowance
The level you design to depends on the development's flood risk vulnerability and its flood zone. The EA's climate change allowances for peak river flow (updated 27 May 2022) say, in Flood Zones 2 or 3a:
"essential infrastructure – use the higher central allowance";
"more vulnerable – use the central allowance";
"less vulnerable – use the central allowance".
The percentages are set by management catchment, from the peak river flow map. The Product 4 gives them for your location, as Figure 2 shows.
The model may not match them. The package warns: "The climate change data included in the models may not include the latest flood risk assessment climate change allowances." The River Trent model held +20%, +30% and +50% runs, while the allowances for the location were 29%, 39% and 62%. The FRA then has to say which run it uses and why, or adjust the level.
Check the local Strategic Flood Risk Assessment (SFRA) as well. It often sets the event and the freeboard. The Greater Nottingham SFRA (2017), as the West Bridgford FRA quotes it, requires minor development to sit at least 300 mm above the 1% AEP plus 30% climate change modelled level.

Illustrative AI image; not a real site or an AFC project.
Worked example: a generator at West Bridgford, from objection to permission
Rushcliffe Borough Council application 25/01976/FUL was for a diesel standby generator in the car park of an existing high-rise residential building in West Bridgford, Nottingham. It powers the firefighting lifts and life-safety systems if the mains supply fails. The site is in Flood Zone 3, next to the River Trent.
The first FRA and the objection. AFC's first FRA (October 2025) had no Product 4 data in it and treated the generator as plant that would not be needed in a flood. The EA objected (reference LT/2025/129619/01-L01). In the words of AFC's revised FRA, the EA "objected on the grounds that the submitted Flood Risk Assessment failed to adequately consider how flooding events, including extreme events, would affect the proposed infrastructure". In a follow-up email the EA pointed out that the NPPF classes "electricity supply including generation" as essential infrastructure.
The data. The Product 4 (EIR/2025/36206) was dated 20 October 2025. Its River Trent model gave 23.83 mAOD at the sample points around the generator for the defended 1% AEP +30% event (Figures 4 and 5).
The level. The revised FRA (Rev 2, 14 January 2026) states: "At this location, the design flood level is 23.83mAOD, establishing a minimum finished floor level requirement of 24.13mAOD." The generator was raised to 24.13 mAOD, "positioning it 300mm above the modelled flood level of 23.83mAOD (representing a flood depth of 0.22m at the site during the 1 in 100 year plus 30% climate change event)". The 300 mm comes from the Greater Nottingham SFRA requirement for minor development.

Figure 6. The generator against the Product 4 level: 23.83 mAOD design flood level, 24.13 mAOD plant level.
The result. The EA withdrew its objection by email the day after Rev 2 was sent, and formally on 18 February 2026: "We rescind our previous objection and are satisfied that the proposal now meets the requirements of being safe from flooding for the lifetime of the development". Rushcliffe granted permission on 10 July 2026. Condition 4 requires that "The generator shall be installed 24.13 metres above Ordnance Datum (AOD)".
Raising the plant 540 mm took the unit to 2.44 m overall, against the case officer's earlier comfort limit of about 2.1 m. The officer accepted it, but it needed a separate check. When a flood level raises plant, tell the case officer early.
The project is written up in full in the West Bridgford generator case study. Our guide to an Environment Agency objection on flood risk covers the objection stage in more detail.
When the EA sends Products 5, 6 and 7 instead
Some EA area teams now answer a Product 4 request with the raw model data. In 2026 three areas did this on AFC jobs:
Hertfordshire and North London, for a garden outbuilding in Twickenham: shapefiles and River Crane (AECOM 2024) Product 5 and 6 data under a Conditional Licence, by temporary download link, with the area's own guidance on using Product 6 data in an FRA;
Kent, South London and East Sussex, for a tidal Thames site in Richmond: Products 5 and 6 for the Thames Tidal Upriver Breach Modelling 2017 and Products 5, 6 and 7 for the Lower Thames (Datchet to Teddington) 2023 model, by download link;
Wessex, for three new homes in Bristol: Products 5, 6 and 7 for the Bristol SFRA 2019 model and the Bristol Avon Flood Strategy 2023 baseline model, in October 2026.
The Kent, South London and East Sussex team put it this way: "Where appropriate, we supply the data in its raw form (Product 6), as opposed to in the Product 4 and/or 8 PDF format."
What arrives is a set of files, not a level. Product 5 is the model report. Product 6 is the model outputs, usually maximum level and depth grids for each event, plus the reports. Product 7 is the model input files, for re-running the model. The FRA has to read the level from the grids itself, which takes GIS work and should be in the fee.

Figure 7. From the data request to the floor level, by either route.
The Twickenham example
For the garden outbuilding in Twickenham, AFC read the River Crane Product 6 grids at the site. The design flood level is 6.81 mAOD, for the 1% AEP event with a 54% upper end allowance, at the frontage. The floor is set at 7.11 mAOD, 300 mm above it, as the EA's covering note required for that model: "the finished floor levels should be set to 1 in 100-year flood level + climate change allowance + 300mm." Flood-resistant construction runs to 7.41 mAOD.
The EA also asked for the FRA to show its working in a set format: a labelled 1D node map and table, and a 2D node map, for all relevant events. Present them the way the EA asks, or expect a request for them.

Figure 8. Where the EA sends grids, not a level: site LiDAR levels set against the modelled design level (Twickenham, 2026).

Figure 9. The levels the FRA took from the Product 6 grids and the LiDAR.
Two checks came out of that job. The survey had been drawn on an arbitrary local datum about 3.32 m above mAOD, so the floor looked 3 m above the flood level when it was about 0.2 m above it. The architect raised the floor by 110 mm to 7.11 mAOD. Check every drawn level is in mAOD before comparing it with EA data.
The flood zone also changed during the job. The site was in Flood Zone 2 in February 2026 and in Flood Zone 3 by October 2026, after the EA adopted the River Crane 2024 model. The application was submitted on 19 October 2026 and is undecided. More detail is on the Cole Park Road case study.
Proving a site "dry" from model data: five checks
A grid that shows no water at your site is evidence only if the site is inside the model. On a small residential new build in Bristol, AFC's own Revision 3 took 10.26 mAOD from New Cut river channel nodes 220 to 280 m away, while the 2D result for the same run was dry at the site. The case officer asked how those figures fitted, and the addendum had to correct them in a table. The checks below came from that correction:
Show the site is inside the 2D model domain. Use a run of the same model that wets the cell, the Product 4 2D table, or the domain files in Product 7. A point outside every model is "outside the models", never "dry".
Find the nearest model nodes at the plot. They may be a culvert rather than the river. In Bristol they were culvert manholes 43 to 79 m away, not the New Cut nodes 273 to 296 m away.
Sample the 2D grids at those nodes.
Take LiDAR along lines from the site to each node, to show the ground that holds the water off and whether a river level exceeds all the ground in between.
Table which EA product was used for what, and map the nodes and LiDAR lines at site scale.
Qualify every "dry" as "as far as the models reach". The EA's guidance on using modelling for flood risk assessments puts the responsibility on the applicant: "It's your responsibility to check the suitability of an existing model for your development." It lists what to check, including whether the model "represents current risk" and "makes use of current climate change allowances".
One more trap from the same family. A West Midlands Product 4 for the Warwick District site held two models that disagreed, and the local river model did not represent the watercourse that floods the site. Take the design level from the source that floods the site.

Illustrative AI image; not a real site or an AFC project.
Waiting for the data: can the application go in?
Yes, if the FRA is honest about what it is waiting for. No, if it fills the gap with a figure the data later contradicts.
Provisional levels, labelled. For the householder site in Warwick District, the FRA was issued to the client on 3 November 2026 with levels from LiDAR and the flood map, stated as provisional, while the Product 4 was awaited. The Product 4 arrived on 5 November and confirmed the provisional 62.10 mAOD design level and the 62.65 mAOD residual level. Nothing in the report had to be withdrawn.
A generic recommendation, withdrawn. At Dorney, AFC's first FRA went out before the Product 4 with a generic recommendation to set the floor 300 mm above the flood level. It alarmed the architect, who asked whether a householder extension could instead match the existing floor with flood resistance and resilience. The Product 4, which took about 9 days, then showed no 1% AEP or climate change grid points on the site, which is in Flood Zone 2. The only level was the 0.1% AEP undefended level of 21.97 mAOD. The revised FRA adopted 21.97 mAOD as a precautionary design level. The extension matches the existing floor of about 22.1 mAOD, with demountable barriers, water-resistant construction to 600 mm and first-floor refuge. The architect accepted it. The Elm Farm, Dorney case study sets it out.
Data that arrives and is never used. On a tidal Thames site in Richmond, AFC's FRA was issued on 16 February 2026, before the EA's model data arrived, and revised on 3 March 2026. The revision quoted no level, depth or hazard from the Product 5 and 6 data the EA had sent. When the data arrives after the first issue, the next revision has to use it.
If you bought it, quote it
At Maidenhead, the Royal Borough of Windsor and Maidenhead permitted a house extension (26/01427/FULL) on 6 August 2026. AFC had ordered the Product 4, which gave about 25.17 mAOD for the 1% AEP +35% event and about 25.33 mAOD for the 0.1% AEP event in the nearest cells. Our FRA did not quote either level or compare it with the floor. It relied on the extension lying outside the 1% AEP plus climate change extent.
The council accepted that, but only because of where the footprint was. The officer wrote: "However, as the dwelling and proposed extension would be located outside Flood zone 2, flood levels are not given. In this particular circumstance, and taking a proportionate approach, the FRA provides appropriate details on mitigation".
Where the footprint is in Flood Zone 2 or 3, RBWM officers check the FRA against the EA's standing advice. That means the Product 4 levels and the floor level in mAOD, with the floor at least 300 mm above the design flood level, or flood resistance and resilience to 600 mm above it. Our guide to flood risk standing advice for extensions sets out that test, and our flood compensation guide for extensions covers the storage side.

Illustrative AI image; not a real site or an AFC project.
What to submit
For a site in Flood Zone 2 or 3 with EA modelled data, the FRA should contain:
the data itself in the appendix: the Product 4 package, or for Products 5 to 7 the extracts used (the node maps, level tables and grid samples, in the format the EA asked for);
the model and the run the level comes from: model name and date, scenario (defended or undefended), event and climate change allowance, with a sentence on why that allowance applies;
the design flood level in mAOD at the footprint, and which point or grid cell it was read from;
the floor or plant level in mAOD and the freeboard, with the SFRA or EA requirement that sets it;
ground levels in mAOD, from LiDAR or a survey tied to Ordnance Datum, and the flood depth on site;
any provisional level labelled as provisional, with the date the data was ordered;
floodplain compensation, safe access and resilience, where the levels call for them;
a flood risk activity permit check if the works are within 8 m of a main river or flood defence, or 16 m of a tidal main river (EA permit guidance).
Planning Practice Guidance paragraph 022 (Reference ID 7-022-20220825) says that for "large or vulnerable developments in areas of high risk, developers should consider consultation with the Environment Agency and/or any other relevant flood risk management bodies for more detailed advice in advance of submitting their planning application." Ordering the data early is the first step of that.
Frequently asked questions
What is Environment Agency Product 4?
Product 4 is the Environment Agency's site data package for a flood risk assessment. It gives modelled flood levels and extents for your site, with defences, past floods and breach hazard where available. The EA describes it as "a detailed FRA map" on its planning permission guidance.
How long does it take to get Product 4 from the Environment Agency?
The EA says the local team will send Product 4 "within 20 working days". On AFC's recent jobs it has taken about 9 days, but plan for the 20 days and order it the day the job starts.
How much does Product 4 cost?
The EA's guidance gives no charge for Product 4; charging information was removed from it in 2016. The cost in practice is the consultant's time to read the data and set the level.
What is the difference between Product 4 and Products 5, 6 and 7?
Product 4 is a PDF with the levels already extracted for your site. Product 5 is the model report, Product 6 the model outputs such as level and depth grids, and Product 7 the model input files. With Products 5 to 7 the FRA has to read the level from the grids itself.
Can I submit my planning application before the Product 4 data arrives?
You can, if every level in the FRA is labelled provisional and the report says the data has been ordered and an update will follow. Do not submit a generic level such as "300 mm above the flood level" that the data may contradict. Our Dorney case study shows why.
The EA sent me Product 6 files instead of a Product 4. What do I do with them?
Product 6 files are model output grids that need GIS software to read. A flood risk consultant samples the grids at your footprint for the right event and climate change allowance, and presents the node maps and level tables the EA asks for. Download the files at once, because the links can expire.
Do I need Product 4 if my site is in Flood Zone 2?
Usually yes. The EA advises requesting Product 1 and Product 4 for all development. In Flood Zone 2 the Product 4 may show only a 0.1% AEP level on the site, as it did at Dorney, but that level still sets the precautionary design level.
Is Product 4 still called Product 4?
The EA now issues it as "flood risk assessment data", and the package says "This information was previously known as a product 4." The gov.uk guidance still calls it product 4.
Get the level right first time
A Product 4 level in the FRA, read from the right point and the right run, is what the EA looks for. Most of the objections and corrections above came from a missing level, a level read in the river channel, or data that arrived and was not used.
If you have a council letter asking for Product 4, or a folder of Product 6 files you cannot open, send us the site details through the website. We will order the data, read it and set the levels in your FRA.